Project introduction

Project title : Establishment of Coastal Water Park
Project Description :

Establishment of a water park in the Chabahar Free Zone area is the goal of this investment plan. This water park is intended to provide recreational services to residents, travelers of Chabahar, and residents of neighboring cities and countries. The park will utilize water-based entertainment tools and activities including water slides, pools, and artificial rivers. The design of this recreational-tourism complex, primarily focusing on water games, aims to promote people's connection with nature, elevate health levels, and foster tranquility within the community. Additionally, implementing this plan will result in economic development, job creation, increased human interactions, and the provision of recreational facilities, consequently attracting tourists.

Annual Capacity : 1,320,000 Tickets

Project status

Access to raw materials :
Sales :
Construction period :
Project status :

Financial structure

Fixed capital : 6,390,310,000,000 Rate of return on capital :
Working capital : 102,779,000,000 Payback Period (PBP) : 3
Foreing currency required : Net present value (NPV) : 189,937,000,000
Total investment :
Internal rate of return (IRR) : 27

Other

Type of the project : establishment
Legal structure of the company : governmental





Above mentioned figures are subject time of investment